This report presents the financial position
for the authority as at September 2019
RESOLVED
1. That the financial reporting data for Quarter 2, month 6, relating to revenue budgetary control, showing a forecast net positive variance at year-end of £1,478k, -0.3% of gross budget be noted.
2. That the contents of Section 4 and the amendments to the Capital Programme contained in Appendix 5b of the Cabinet report be noted and the amendments in the Table below be approved:
Scheme |
2019/20 Budget |
2020/21 Budget |
2021/22 Budget |
2022/23 Budget |
Narrative |
Civic Centre – Civic Centre Lighting |
(300,000) |
|
300,000 |
|
Life expectancy greater than expected – slipped to 2021/22 |
Highways & Footways – Highways bridges and structures |
(120,000) |
120,000 |
|
|
Re-profiled in accordance with projected spend |
Capital Contingency |
|
|
|
108,900 |
Transferred from school equipment loans to the Capital Contingency |
School Equipment Loans |
(108,900) |
|
|
|
|
Total |
(528,900) |
120,000 |
300,000 |
108,900 |
|