Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Providing an update on the progress of the
delivery of the first 4 council homes sites, as agreed at Cabinet
in July, and an overview of recommendations of sites and delivery
routes to enable the Council to deliver its long term ambitious
target of 400 genuinely affordable sustainable homes underway by
2026.
RESOLVED:
A. That Cabinet noted the update and recommendations arising from the externally led asset review on how the Council’s ambition to deliver 400 new council homes can be met.
B. That Cabinet agreed not to dispose of the next tranche of sites, as previously agreed, and instead allocates the sites for the affordable homes programme either through Council led delivery or development partnership.
C. That Cabinet approved design and viability work to being on the following three sites: Worsfold House, Chaucer Centre and Gifford House.
D. That Cabinet approve the commencement of soft market testing with the private sector on a partnership arrangement to deliver homes at the land at Battle Close.
E. That Cabinet approved the allocation of the expected capital receipt from the sale of the land at St George’s Rd to support the design work for the three sites highlighted above in C, and to support procurement for development through a partnership for the land at Battle Close, if soft market testing is positive.
F. That the land at 111-127 The Broadway SW19 (also known as P4) be brought to the market and that the Executive Director of Housing and Sustainable Development, in consultation with the Cabinet Member for Housing and Sustainable Development, be authorised to agree terms for a disposal.
G. That the capital receipt from the sale of the land at 111-127 The Broadway SW19 is ringfenced to support the delivery of the Council’s affordable homes programme.
H. That Cabinet noted the finance, timescale and officer resource implications for the continuing programme, including the conclusions from a report into the viability and timing of setting up a new Council Housing Revenue Account
I. That Cabinet noted the proposed Governance arrangements for ensuring oversight of the housing programme moving forward
Report author: Lucy Owen
Publication date: 20/11/2023
Date of decision: 16/11/2023
Decided at meeting: 16/11/2023 - Cabinet
Effective from: 24/11/2023
Accompanying Documents: