Decision Maker: Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: Yes
1. ANPR cameras
provision and implementation of:
18 ANPR cameras for school streets enforcement, via approved CIL
funding in year 1 of the contract.
53 replacement ANPR cameras to replace the existing Tyco supported
cameras in 2025 subject to a further business case.
Provision within the terms of the contract to purchase additional
ANPR cameras for MTC or other environmental purposes.
Provision of software and other associated technologies for the
processing of PCNs and relevant data
2. Public CCTV Upgrade and Maintenance
CCTV camera upgrade – upgrading of 150 CCTV public space
cameras from analogue to HD quality. Upgrading the transmission
method by introducing a hybrid fibre-wireless solution that will
greatly reduce the dependence on BT and Virgin Media fibre.
3. CCTV maintenance contract for public space and ANPR
providing preventative maintenance, cleaning and repairs on
council’s public space and ANPR cameras
RESOLVED:
A. That Cabinet approved the award of a contract for CCTV and ANPR upgrade including maintenance to the successful bidder identified in Appendix 1 for a term of four years with the option to extend for a further 12 or 24 months.
B. That Cabinet delegated authority to exercise the option to extend this contract to the Director of Environment and Regeneration.
Report author: Adrian Rutkowski
Publication date: 13/10/2021
Date of decision: 11/10/2021
Decided at meeting: 11/10/2021 - Cabinet
Effective from: 19/10/2021